How to set a due date after a task is done

avdyk says:
Hi,
Is it possible to set a due date x day(s) after another task is done?
Example:
- task A: buy a new laptop
- task B: configure the laptop (due date: 5 days after task A is done)...
Maybe there are other ways to achieve this? (sub task?)
Is it possible to set a due date x day(s) after another task is done?
Example:
- task A: buy a new laptop
- task B: configure the laptop (due date: 5 days after task A is done)...
Maybe there are other ways to achieve this? (sub task?)

andrewski (Remember The Milk) says:
Hi avdyk,
Thanks for getting in touch. It's not possible to do that in two separate tasks, but you can approximate this with a repeating task and subtasks:
* Your task could repeat after 5 days
* Your subtasks could be in sequence and would be available 5 days later ready to complete.
Hope this helps a bit!
Thanks for getting in touch. It's not possible to do that in two separate tasks, but you can approximate this with a repeating task and subtasks:
* Your task could repeat after 5 days
* Your subtasks could be in sequence and would be available 5 days later ready to complete.
Hope this helps a bit!